E-mail Sent

Date

Subject

Email Content

10/05/2016

CA_Activités cette semaine / TLC_ Activities this week

THIS WEEK’S ACTIVITIES

 Learning Centre:

·         Pile caps concrete pouring

·         Concrete formwork for walls

·         The objective is to complete the ground floor slab by June 0, 2016.

 

Renovations inside Lamoureux:

 

·         Column reinforcement at ground floor and 2nd floor (East side)

·         Renovations at new clinic at 3rd floor.

·         Construction at corridors 200j and 200c

·         Construction at classrooms 242 & 243

·         Deficiency corrections at the Resource centre

 

03/04/2016

uO LC/CA_Activités semaine prochaine / Activities next week MAJOR MILESTONE/ÉTAPE IMPORTANTE

NEXT WEEK’S ACTIVITIES

 

Learning Centre :

·         Piling Work – North Side (45% complete)

·         Preparation for concrete pours

 

Resource Centre within Lamoureux:

·         Completion of construction work

o    Wall painting

o    Flooring material installation

o    Fixed millwork installation

o    Installation of new mechanical/electrical system

o    Ceiling structure installation

o    Computer cabling installation

·         City of Ottawa occupancy inspection & permit

·         The following week, the University will initiate the move into the newly renovated spaces.

 

02/22/2016

uO LC/CA_Activités cette semaine / Activities this week

THIS WEEK’S ACTIVITIES

 

Learning Centre :

·         Piling Work – South Side

·         Excavation of deep clay soil

 

Resource Centre within Lamoureux:

·         Wall painting

·         Flooring material installation

·         Fixed millwork installation

·         Installation of new mechanical/electrical system

·         Ceiling structure installation

·         Computer cabling installation

 

02/16/2016

uO LC/CA_Activités cette semaine / Activities this week

THIS WEEK’S ACTIVITIES

 

Learning Centre :

·         Start of piling Work – South Side

·         Excavation of deep clay soil

 

Resource Centre within Lamoureux:

·         Wall painting

·         Flooring material installation

·         Fixed millwork installation

·         Installation of new mechanical/electrical system

·         Ceiling structure installation

·         Computer cabling installation

 

02/16/2016

uO LC/CA_Piling/Pieux

Please note that the Learning Centre piling installation has started this morning and will continue for a period of around 6 to 8 weeks.

 

01/18/2016

uO LC/CA_Noisy work on Monday/Travaux bruyants lundi

I am sorry to announce at this time, but for part of the day Monday, noisy construction work will take place at the 2nd floor of Lamoureux.  We aim to perform the noisiest work in early morning but it may extend depending on the conditions found on site.  Some classes have been moved to minimize the impact on the student population.

 

01/18/2016

uO LC/CA_Activités cette semaine / Activities this week

 

THIS WEEK’S ACTIVITIES

 

Learning Centre :

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Tie-back installation

 

Resource Centre within Lamoureux:

·         Column reinforcement – Concrete pour

·         Pouring of concrete floor leveller

·         Demolition and new mechanical system installation

·         Electrical systems installations.

·         Office wall construction

 

01/06/2016

LC - This week's site activities

Voici les activités de la semaine :

 

Resource Centre

§  2nd floor – Grinding of existing slab

§  2nd floor - Chipping of existing topping (CCO #08)

§  Start of layout of partitions

§  2nd floor - Ductwork demolition

§  2nd Floor – Above ceiling electrical rough-in

§  1st and 2nd Floor – Water damage repairs (Xpertek)

 

Learning Centre

§  Installation of 2nd row tie backs – West Elevations

§  Installation of 2nd row of whalers and tensioning of tie-backs – East and South Elevations

 

12/14/2015

LC_ CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

Learning Centre :

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Tie-back installation – South end

 

Resource Centre within Lamoureux:

·         Column reinforcement

·         General demolition work

·         Demolition and capping of existing mechanical and electrical systems.

 

12/08/2015

LC_ CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

Learning Centre :

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Tie-back installation – South end

 

Resource Centre within Lamoureux:

·         Column reinforcement

·         General demolition work

·         Demolition and capping of existing mechanical and electrical systems.

 

11/30/2015

CA_Activités cette semaine / LC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Excavation continues

·         Tie back installation continues

·         Underpinning work  at Tunnel & Stairs ongoing

·         Shoring wood lagging Work

 

EXISTING BUILDING – RESOURCE CENTRE (LAMOUREUX)

·         Column reinforcement (noisy activity for the next few weeks)

·         Demolition

·         Hoarding installation

 

11/26/2015

Centre d'apprentissage_Fermetures de ures et trottoirs / Learning Centre_Road and sidewalk closure UPDATE

The duration of the sidewalk closure between Brooks and LMX is extended because unexpected existing underground services were discovered and must be addressed.  I will inform you of a date for the reopening as soon as it becomes known.

 

Merci!

 

11/20/2015

Centre d'apprentissage - Fermetures de rues et trottoirs | Learning Centre - Road and sidewalk closure

Hello,

 

This is to inform you that the work being performed at the pedestrian walkway next to Brooks will only be completed by end of day on Monday.

 

11/16/2015

CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

Excavation, Shoring, Piling And Rock Anchors

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Capping of 3 abandoned domestic water services under the pedestrian

·         Connection of new sanitary connection under Marie Curie Private

 

Resource Centre Renovations Inside Lamoureux Hall

·         M&E cap and make safe

·         Demolition

·         Hoarding walls installation

 

11/09/2015

CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

Excavation, Shoring, Piling And Rock Anchors

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Completion of pile drilling for new stairs inside existing Lamoureux

·         Tie-back installation – East wall

 

11/02/2015

CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Excavation – South end

·         Excavation of deep clay soil

·         Shoring wood lagging work

·         Completion of pile drilling for new stairs at existing LMX

·         Start of tie-back installation – South end

10/26/2015

CA_Activités cette semaine / TLC_ Activities this week

LEARNING CENTRE : THIS WEEK’S ACTIVITIES

 

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Excavation – North End

·         Shoring wood lagging Work – Nord and west sides

·         Completion of the shoring battered piles – North End

·         Completion of pile drilling for new stairs at existing LMX (noisy activity)

·         Start of Tie back installation – North End

 

EXISTING BUILDING (LAMOUREUX)

·         Completion of building envelope insulated tarping at existing exterior wall.

 

10/19/2015

CA_Activités cette semaine / TLC_ Activities this week

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Excavation – North End

·         Shoring wood lagging Work – Nord and west sides

·         Completion of the shoring battered piles – North End

·         Start of pile drilling for new stairs at existing LMX (noisy activity)

 

EXISTING BUILDING (LAMOUREUX)

·         Building envelope insulated tarping at existing exterior wall.

 

10/05/2015

CA_Activités cette semaine / TLC_ Activities this week

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Start of excavation (1st lift 1A) – North End

·         Start off shoring wood lagging Work – East Side

·         Completion of the shoring battered piles – North End

·         Start of pile drilling for new stairs at existing LMX (noisy activity) (Was to be performed this week, but delayed to next week due to a mechanical failure)

 

EXISTING BUILDING (LAMOUREUX)

·         Start of building envelope insulated tarping at existing exterior wall.

 

09/29/2015

CA_Activités de la semaine / TLC_ Activities of the week

EXCAVATION, SHORING, PILING AND ROCK ANCHORS

·         Completion of the shoring battered piles Work – South End and west side

·         Start of pile drilling for new stairs at existing LMX (noisy activity)

·         Start of excavation (1st lift 1A) – North End

 

EXISTING BUILDING (LAMOUREUX)

·         Completion of the boarding and insulating Work of the 3rd and 4th level windows openings at the “old” amphitheater.

 

09/23/2015

CA_Activités de construction / TLC_Construction activities

Starting on Monday 28 September 2015, piles will be installed for the new exterior stairwells at the Learning Center.  This work will be executed over a period of 5 to 10 business days, depending on conditions incurred on site.  Since these stairwells are directly connected to Lamoureux, this work may generate higher noise levels than what is present at the site currently.  The Registrar has already taken steps to minimize the number of classes given to Lamoureux and for classes that remain, following discussion with the Registrar, the professors will receive instructions should they need to cancel their classes due to construction activities.

 

09/16/2015

TLC_Pile driving / CA_Pieux foncés IMPORTANT

The Learning Centre piling equipment is in place. The team will make some tests tomorrow and the installation of piles required for the shoring will begin Friday and continue for the next three weeks. During this period we will better understand the noise levels generated during work and their impact on student life. Our options are limited, but we can then determine whether adjustments are possible.

09/14/2015

CA_Activités de la semaine / TLC_Weekly construction activities

Here are the week’s activities for the Learning Centre:

§  Removal of precast panel and windows @ 3rd and 4th floor,

§  Demolition and removal of foundation of demolished building (top of pile caps),

§  Mobilization of Piling rig and equipment,

§  Start of Shoring work (North Side),

§  Start of test pits.

 

09/04/2015

TLC Noise today / Bruit aujourd’hui au CA.

As part of the ongoing demolition of the old Resource Centre you may periodically experience higher than normal levels of noise and vibration generated from the hoe ram. These will be limited to short intervals throughout the day on Friday, and potentially Saturday, and only as required.

09/02/2015

Odeur de fumée | Smoke smell

Hello,

 

Following the alarm this morning, it is possible that smoke smell persists in the offices and corridors of the fourth floor. There is nothing to worry, firefighters audited and everything is normal.

 

08/31/2015

Centre d’apprentissage : Activités de la semaine – Learning Centre : This week’s activities

Please find this week’s acitvites for the Learning Centre.  The week’s activities will be noisy.

 

Demolition work

§  2 Storey Building

  • Start of removal of precast panel – Monday
  • Inspection of scaffolding – Monday
  • Cutting /Disconnecting of South section – Tuesday
  • 2nd floor – Start of saw cutting concrete slab – Wednesday
  • Start of demolition – Thursday

·         Lamoureux:

  • Precast panels removal – South Section
  • Windows removal – South Section

 

Excavation work

·         Site mobilization – Trailers

 

08/25/2015

Centre d’apprentissage DEMOLITION / Learning Centre DEMOLITION

We recognize that the Learning Centre demolition activities underway this week are particularly noisy and disruptive.  Our goal is to complete the demolition work of the former resource centre and the exterior pre-cast concrete siding removal as quickly as possible, ideally before September 7.  All seems to indicate that it is achievable, which will reduce the disruptions when classes start in September.  We appreciate your patience and collaboration during this period.

08/24/2015

LCA_Activités de construction la semaine prochaine / TLC_Construction activity next week.

For your information, here are the planned construction activities for the week of August 24 to August 28:

·         Demolition of the stairwell C (northeast) begins Tuesday or Wednesday. 

·         Cut concrete at the existing amphitheaters floors and former Resource Center

·         Precast concrete siding removal alongside siding panels at East and South facades

·         Complete the erection of temporary walls

·         Complete disconnection of the mechanical and electrical systems.

·         Relocation of exterior natural gas lines (on site)

·         Start of exterior shoring work. (on site).

 

THE DEMOLITION ACTIVITIES DURING THIS WEEK WILL BE NOISY AND DISRUPTIVE TO THE OCCUPANTS.

 

08/19/2015

Odeur de feu | Fire odor

Hello,

 

With the construction today at Lamoureux, you may smell a fire odor in your office or in corridors. There is nothing to worry about. Fell free to contact Céline Morin celine.morin@uottawa.ca if you have any question. 

 

08/18/2015

Construction du Centre d’apprentissage | Learning Centre Construction

Hello,

 

Please be advised that today, August 18, 2015, Pomerleau will be removing the windows in rooms LMX 374 & 466.  This work may inconvenience the occupants for about an hour.  We are sorry for the late notice and for any inconvenience.

 

Thank you

 

08/17/2015

Activités de construction prévues – Semaine du 17 août | Planned construction activities – Week of Augut 17

For your information, here are the planned construction activities for the week of August 17 to August 23:

  • Demolition of the pre-cast concrete on the North and East facades.
  • Removal of some windows (at unoccupied offices at East and South facades).
  • Window protection at the occupied perimeter offices. 
  • Interior demolition at the amphitheatre level 1.
  • Demolition of the ceiling at the former level 2 Resource Centre.
  • Sawing of the foundations at stairs C and rooms of the former Resource Centre.
  • Erection of temporary walls at level 2 of the former Resource centre.  
  • The end of the demolition work is scheduled in September 2015.

 

IMPORTANT NOTICE: THE REMOVAL OF THE EXTERIOR CONCRETE PRA-CAST PANELS IS PROGRESSING.  WINDOWS WILL BE BARRICADED AT THE OCCUPIED EXTERIOR PERIMETER OFFICES.  THE DEMOLITION ACTIVITIES WILL BE NOISY AND DISRUPTIVE TO THE OCCUPANTS.

 

07/31/2015

Construction du Centre d’apprentissage | Learning Centre Construction

IMPORTANT – PLEASE READ CAREFULY

 

Here is an update on the work coming up next week in relation to the construction of the Learning Centre:

 

-          Removal of the portable.

-          Investigation on the precast panel, which might result in noise disturbances.

-          Removal of the light post.

-          Demolition of ceiling and furniture in the amphitheater.

 

Thank you for your continued cooperation.

 

07/16/2015

Centre d’apprentissage – avis du service des Immeubles | Learning Centre – notice from Facilities

Hello,

 

Please note that some preparatory construction work will begin next Monday, July 20, 2015.

 

The following places will be primarily affected:

 

  • The ceilings hallway 101B and hallway 101C. Access to the resource center will be affected, but will be maintained. If work restricts access to the rooms, work will be performed after regular hours of operation.
  • Creation of a temporary hallway adjacent to Room 254.
  • Temporary protection in the north wall of the secretariat. Before its undertaking, work will be coordinated with the occupants.
  • Protective walls in Hall 101F: This area will be blocked and will now be part of the construction area. This includes washrooms outside the amphitheater 122 on the ground floor.

 

The Pomerleau constructors are preparing a plan of the affected areas, however, since work is immediate and that the plan has not been finalized, I thought I would let you know immediately.

 

Thank you

 

07/08/2015

fermeture électrique – LMX – electrical shutdown

Facilities are planning an electrical shutdown in LAMOUREUX HALL, on Thursday, July 9th from 5:00 a.m. to 7:00 a.m. The shutdown will affect the lights and electrical outlets of the building.

 

Information: Daniel Ouellette, Supervisor, Electrical maintenance, ext. 6996 or douellet@uottawa.ca

 

Back to top